BEWI CIVILS PRODUCTS PLAY A KEY ROLE IN ROYAL BERKSHIRE ARCHIVES REFURB PROJECT
A major extension to the existing Berkshire Record Office and associated infrastructure
works have recently been successfully concluded, thanks to the involvement of civils products supplied by BEWI.
Designed using Building Information Modelling (BIM), the Royal Berkshire Archives Extension is intended to enhance the heritage offer, improve the services available and provide enhanced secure long term storage for the collections housed in the building.
The BEWI products used were ClayMaster to protect against horizontal heave, Pile Collars in various sizes and with different pile size holes and some pile collar cut-offs set to accommodate the location of the piles within the trenches, as well as Bespoke Angle Cut Infill Panels. HeaveMaster GHP (Ground Heave Protection) was used both below the slab in low and high grades, and also below the beams, in a variety of widths, along with Formwork Tape.
The main contactor on the project was Feltham Construction. Blanchard Wells, who carried out the groundworks, purchased the BEWI product directly.
The total duration of the build was one year and the plot size was approximately 200m2 below the slab and approximately 150LM of below beam product, with an overall build size of 474m2.
The customer was very happy with the performance and ease of use of the BEWI products. The site contact from Blanchard Wells, said: “We liked the fact that BEWI offered cuts in different sizes for the below-ground beams, as this helped speed up the install process and saved the installers time due to not having to cut the product to the correct size. This was also a benefit of the Pile Collars for the same reason, particularly since some of the piles were offset and the pile holes were pre-cut to this offset.
“Different grades and widths of product were required on site and it was easy to find the different widths or types of products, because of the labelling which BEWI had put on each pallet.
“The bespoke angle infills saved time since this reduced the cutting required and potential excess waste on site. We are likely to be looking at the BEWI insulated slab product on future projects, as this helps speed up the install process by having the insulation and heave products integrated.”